SidewalksDelayed
DeCastro Street Sidewalks Improvement
Demolition and reconstruction of sidewalks to accessible standards, drainage reinstatement, landscaping and wider parking-lot entrances. The RDA says tree roots beneath the pavement are the underlying cause and that temporary repairs have not solved it.
- Contract
- $798,108.74
- Contractor
- TMB Enterprises
- Signed
- 30 Jul 2026
- Duration
- 120 days
- Projected completion
- Feb 2027
- Trees
- Mahogany, White Cedar and Yellow Poui removed; Bottlebrush and Verawood to be planted
Delayed. On 8 September 2026 the RDA postponed the start, citing incomplete contractual and administrative requirements. No new start date has been announced. The tree removals are publicly contested and the Leader of the Opposition asked for a postponement.